Scope creep
With all forms of appointment it is important that there is clarity about the scope of services being provided otherwise there may be uncertainty about who is responsible for which aspects of the project, what fee is chargeable, what services are within the agreed fee and what services might be considered ‘extras’.
For this reason, appointment agreements often include, or refer to, a ‘schedule of services’ (sometimes described as ‘scope of services’ or ‘services schedule’) setting out precisely what services a consultant will be performing on a project. Schedules of services may also be prepared for contractors where they are carrying out design work, or for consultants appointed by contractors on design and build projects.
Changes to a project may impact on the scope of services required. Where this is controlled, it may be described as a change of scope, and this should be carefully documented and may be reflected in changes to the appointment agreement, or fee. However, when it is not a controlled process it can be referred to as ‘scope creep’. This may be as simple as a verbal request from the client (or from one part of the client organisation) to carry out a piece of work, without a proper assessment of whether that work is included in the existing fee, or whether it is an additional service for which additional fee is chargeable, whether it has been authorised, or whether it is a sensible use of the clients finite funds compared to other possible activities.
Typically these requests will in themselves be relatively small, but repeated changes or additions can build up, or ‘creep’ to become significant variations, resulting in continuous growth of the scope of services and a drift away from the original brief, fee or budget.
Scope creep can also refer more broadly to uncontrolled changes to the project itself, for example, increasing the schedule of accommodation required, or the quality expected, or the duration of the project. These uncontrolled changes may not be properly documented, may not be properly assessed in terms of value and may not be reflected in changes to the budget. This can also impact on the fees chargeable, where for example they are calculated as a percentage of construction cost.
Scope creep is one of the main causes of cost and programme overruns.
Scope creep can be avoided by scope management, first assessing and defining the project clearly so that the scope is properly understood, agreed and communicated to all parties, and then introducing change control procedures to ensure that uncontrolled changes of scope are avoided, and where changes are necessary, they are properly assessed, authorised and documented.
A change control procedure should clearly define the process by which changes are requested and approved and who is responsible for those processes, including:
- The reasons for the change.
- Who is requesting the change.
- The consequences of the change, including health and safety, time, quality and cost (and who will bear the cost).
- Proposals for mitigation of any consequences.
- The risks associated with the change.
- Alternatives to the proposed change.
- Time by which the change must be instructed.
There may then be:
- Client evaluation of whether the impact of the change is acceptable and whether the proposal provides value for money.
- Client instructions to the consultant team.
- Contract administrator instructions to the contractor.
The client may have to consider a number of possible changes simultaneously and may therefore need the appropriate information to be able to prioritise them relative to one another.
The need for changes can be minimised by:
- Undertaking thorough feasibility studies, site investigations and condition surveys.
- Ensuring that the project brief is comprehensive and is supported by all stakeholders (including end users).
- Ensuring that legislative requirements are properly integrated into the project.
- Ensuring that risks are properly identified.
- Ensuring that designs are properly co-ordinated before tender.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Abortive work.
- Appointment.
- Change control procedure.
- Cost control.
- Cost overruns.
- Fee proposals.
- Scope of services.
- Variation.
- Value engineering.
- Value management.
[edit] External References
Featured articles and news
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help the homebuilding sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.